Suzhou BISON Successfully Completes the COMEXI F2MC Equipment Relocation Project for Suzhou TIPACK

Suzhou, March 2025 — Recently, Suzhou BISON successfully completed the relocation project of the COMEXI F2MC flexographic printing equipment for Suzhou TIPACK. The project, which lasted one and a half months, was completed by the BISON engineering team with rich experience and a high level of professionalism. They successfully carried out the dismantling, transportation, installation, and commissioning of the equipment, ensuring that it reached its optimal operating condition. The customer highly recognized the service and praised the professional capabilities and spirit of the BISON team.
Project Background: Ensuring Efficient and Safe Equipment Relocation
Suzhou TIPACK, a well-known domestic packaging and printing company, has always been committed to improving production efficiency and product quality. Due to business adjustments and capacity planning needs, the company decided to relocate the COMEXI F2MC flexographic printing equipment to optimize its production layout and further enhance its production capacity.
As an important partner of COMEXI in China, the BISON team, with its extensive experience in the installation, relocation, and maintenance of flexographic printing equipment over the years, provided comprehensive technical support for this project. From the initial planning to the on-site implementation, the BISON team always adhered to the principles of professionalism, efficiency, and safety, ensuring the smooth progress of the relocation process while minimizing the impact on TIPACK’s production schedule.
Project Implementation: Precision Operations to Ensure Stable Equipment Operation
The entire relocation project was divided into several key stages, including equipment dismantling, packaging and transportation, reinstallation, and commissioning. Before the project started, the BISON team had thorough communication with the management team of TIPACK and developed a detailed relocation plan. They also designed contingency plans for potential risks to ensure the smooth progress of the project.
During the equipment dismantling process, BISON engineers strictly followed the technical standards of COMEXI to ensure the safe dismantling and proper protection of each component. In the transportation phase, the BISON team adopted professional protective measures to avoid vibrations or damage that might occur during transit.
After the equipment arrived at the new factory site, BISON engineers immediately began the installation work, ensuring precise alignment of each component. They also conducted a comprehensive inspection of the electrical, pneumatic, and control systems. During the commissioning stage, BISON engineers, in combination with COMEXI’s standard procedures, carried out multiple rounds of testing on the equipment, optimized the equipment parameters, and ensured that production efficiency and printing quality reached the best possible state. Ultimately, after rigorous testing, the COMEXI F2MC flexographic printing machine was successfully put into operation, with all performance indicators meeting or even exceeding expectations.
Customer Feedback: High Recognition of BISON’s Professional Services
The management of Suzhou TIPACK highly recognized the efficient execution and professional services of the BISON team. A company spokesperson said, “This equipment relocation project went very smoothly. The BISON team demonstrated a high level of professionalism and dedication. The equipment has been running very stably after commissioning, ensuring our production schedule. In the future, we look forward to more cooperation with BISON.”
Summary: Deepening Services to Support the Development of China’s Flexographic Printing Industry
The successful completion of this project once again proved the outstanding capabilities of the BISON team in the relocation and commissioning of flexographic printing equipment and further solidified BISON’s good reputation in China’s flexographic printing market. Looking ahead, BISON will continue to uphold the service philosophy of “professionalism, efficiency, and customer first,” providing more companies with high-quality solutions for equipment relocation, installation, and maintenance, and contributing to the high-quality development of China’s flexographic printing industry.

Related Cases

No posts found

Related Products

No posts found

Related Post


Warning: Undefined array key 0 in /home/u292424408/domains/bisonprint.net/public_html/wp-content/themes/astra-child/functions.php on line 166
Suzhou BISON Successfully Completes the COMEXI F2MC Equipment Relocation Project for Suzhou TIPACK

Warning: Undefined array key 0 in /home/u292424408/domains/bisonprint.net/public_html/wp-content/themes/astra-child/functions.php on line 166
Suzhou Bison Deepens Cooperation with Poland's ROTOMETAL to Expand in China's Flexographic Printing Market

Warning: Undefined array key 0 in /home/u292424408/domains/bisonprint.net/public_html/wp-content/themes/astra-child/functions.php on line 166
Suzhou BISON Teams Up with Spain's COMEXI to Showcase at CHINAPLAS 2025, Expanding in the Chinese Market
Scroll to Top